Concrete plate in the bedroom/bathroom done, plastering 1st coat is done everywhere on level 0 and level 1 is done on 100%, already have been start the final (white color) skim plaster on the level 0, plasterboard has been done on the ceilings everywhere, deviding walls on the level 0 has been creater, plumbing has been nearly done, decorative bars has been installed, the atic floors and ceilings has been already farnish on 100% too, el. system complete on 100% |